- CRITICAL PATH ANALYSIS FOR: P&L CONSTRUCTION PROJECT RUN DATE: OCT 28 , 1983
-
- TIME PERIOD = CALENDAR DAYS
-
- ACTIVITY DESCRIPTION FROM TO EST. ACTUAL EARLY LAST EARLY LAST FLOAT C REPORT SUBCONTRACTOR
- NODE NODE TIME TIME START START FINISH FINISH TIME P FINISH NAME
-
- MOBILIZATION 500 510 2 2 OCT4883 OCT4883 NOV1983 NOV1983 0 * WILSON
- GRADE & CLEAR 510 520 5 5 NOV1983 NOV1983 NOV2483 NOV2483 0 * JONES
- REBAR PIERS 520 530 5 5 NOV2483 NOV2483 NOV2983 NOV2983 0 * MILLER
- POUR PIERS 530 550 5 5 NOV2983 NOV2983 DEC0483 DEC0483 0 * ARCHS
- EXCAVATE FOUNDATIONS 550 560 8 8 DEC0483 DEC0483 DEC1283 DEC1283 0 * LEMON
- REBAR FOUNDATIONS 560 570 5 5 DEC1283 DEC1283 DEC1783 DEC1783 0 * BUGMAN
- ANCHOR BOLTS 570 580 2 2 DEC1783 DEC1783 DEC1983 DEC1983 0 * SHECK
- POUR & CURE FOUNDATIONS 580 585 0 0 DEC1983 DEC1983 DEC1983 DEC1983 0 * WILLIS
- STRUCTURAL STEEL 585 587 0 0 DEC1983 JAN0384 DEC1983 JAN0384 15 MEAD
- DECK FILL CONCRETE 590 600 15 15 JAN1384 JAN1384 JAN2884 JAN2884 0 * KNOUS
- WELD STRUCTURAL 587 595 20 20 DEC1983 FEB2584 JAN0884 MAR1684 68 HOM
- FIRE PROOFING 620 625 5 5 JAN2884 FEB2884 FEB0284 MAR0484 31 HEDIN
- PRECAST PANELS 625 650 20 20 FEB0284 MAR0484 FEB2284 MAR2484 31 ROBER
- P.M. FRAMES 600 790 2 2 JAN2884 FEB1584 JAN3084 FEB1784 18 MAST
- WALL FRAMING 600 790 20 20 JAN2884 JAN2884 FEB1784 FEB1784 0 * JONEY
- SHEET METAL DUCTWORK 600 955 40 40 JAN2884 FEB1184 MAR0884 MAR2284 14 FURRER
- ELEC. RGH. IN 620 640 10 10 JAN2884 JAN2884 FEB0784 FEB0784 0 * MACFORD
- MAIN ELEC PANEL 640 790 10 10 FEB0784 FEB0784 FEB1784 FEB1784 0 * MCCALL
- PLUMING RGH IN 620 630 5 5 JAN2884 FEB0484 FEB0284 FEB0984 7 TRAMMEL
- POUR S.O.G. 630 790 8 8 FEB0284 FEB0984 FEB1084 FEB1784 7 WHITE
- STAIRCASES 585 590 25 25 DEC1983 DEC1983 JAN1384 JAN1384 0 * CABELL
- PLUMB. TOP OUT 630 890 10 10 FEB0284 MAR1384 FEB1284 MAR2384 40 BROOK
- ELEC. PULL WIRE & POWER 640 760 10 10 FEB0784 MAR1484 FEB1784 MAR2484 36 GIBSON
- ELEC. FIXTURES/SWITCHES/PLUGS 760 960 5 5 FEB1784 MAR2484 FEB2284 MAR2984 36 GENET
- STAIR FILL 597 710 10 10 JAN1384 MAR1684 JAN2384 MAR2684 63 KALIN
- INSULATION 790 800 2 2 FEB1784 FEB1784 FEB1984 FEB1984 0 * WILSON
- DRYWALL 800 810 10 10 FEB1984 FEB1984 FEB2984 FEB2984 0 * PARR
- CERAMIC TILE 810 850 20 20 FEB2984 FEB2984 MAR2084 MAR2084 0 * MORRIS
- PAINT INTERIOR 810 860 10 10 FEB2984 MAR0984 MAR1084 MAR1984 9 BEREN
- DUMMY 860 870 0 0 MAR1084 MAR1984 MAR1084 MAR1984 9 WILCOX
- STAIN DOORS 870 920 5 5 MAR1084 MAR1984 MAR1584 MAR2484 9 LOPEZ
- FINISH HARDWARE 920 960 5 5 MAR1584 MAR2484 MAR2084 MAR2984 9 BAIR
- METAL SIDING 0 890 2 2 OCT4883 MAR2184 NOV1983 MAR2384 125 KRENCHIK
- ACCESS LADDER 950 960 5 5 FEB1384 MAR2484 FEB1884 MAR2984 40 LEACH
- REGISTERS & GRILLS 955 957 5 5 MAR0884 MAR2284 MAR1384 MAR2784 14 FREEMAN
- BALANCE H.V.A.C. 957 960 2 2 MAR1384 MAR2784 MAR1584 MAR2984 14 TRESH
- TOILET FIXTURES 850 910 5 5 MAR2084 MAR2084 MAR2584 MAR2584 0 * WERST
- TOILET PARTITIONS 910 940 2 2 MAR2584 MAR2584 MAR2784 MAR2784 0 * LOLICH
- PAINT STAIRS 710 960 3 3 JAN2384 MAR2684 JAN2684 MAR2984 63 BUNNING
- CURBS & SIDEWALKS 650 960 5 5 FEB2284 MAR2484 FEB2784 MAR2984 31 MCCLAIN
- FINAL CLEAN UP 960 970 2 2 MAR2984 MAR2984 MAR3184 MAR3184 0 * NORTHRUP
- DUMMY 600 620 0 0 JAN2884 JAN2884 JAN2884 JAN2884 0 * STANLEY
- ROOF HATCH 890 950 1 1 FEB1284 MAR2384 FEB1384 MAR2484 40 OYLER
- DUMMY 587 590 10 10 DEC1983 JAN0384 DEC2983 JAN1384 15 CASH
- METAL DECK WELD 587 597 25 25 DEC1983 FEB2084 JAN1384 MAR1684 63 WOCKFUSS
- DUMMY 810 955 0 0 FEB2984 MAR2284 FEB2984 MAR2284 22 GRUBB
- DUMMY 595 597 0 0 JAN0884 MAR1684 JAN0884 MAR1684 68 COBB
- TOILET ACCESSORIES 940 960 2 2 MAR2784 MAR2784 MAR2984 MAR2984 0 * GRENBERG
-
- THE CRITICAL PATH LENGTH IS 135
- COMPLETE LIST OF CRITICAL PATH ACTIVITIES (THOSE ACTIVITIES DENOTED ABOVE BY *)
-
- ACTIVITY DESCRIPTION FROM NODE TO NODE DURATION CUM.TIME
- ----------------------------------------------------------------------------
- MOBILIZATION 500 510 2 2
- GRADE & CLEAR 510 520 5 7
- REBAR PIERS 520 530 5 12
- POUR PIERS 530 550 5 17
- EXCAVATE FOUNDATIONS 550 560 8 25
- REBAR FOUNDATIONS 560 570 5 30
- ANCHOR BOLTS 570 580 2 32
- POUR & CURE FOUNDATIONS 580 585 0 32
- STAIRCASES 585 590 25 57
- DECK FILL CONCRETE 590 600 15 72
- DUMMY 600 620 0 72
- ELEC. RGH. IN 620 640 10 82
- MAIN ELEC PANEL 640 790 10 92
- INSULATION 790 800 2 94
- DRYWALL 800 810 10 104
- CERAMIC TILE 810 850 20 124
- TOILET FIXTURES 850 910 5 129
- TOILET PARTITIONS 910 940 2 131
- TOILET ACCESSORIES 940 960 2 133
- FINAL CLEAN UP 960 970 2 135
-
- PATH ENDS AT NODE 970
-
- CRITICAL PATH NUMBER 2 STARTING AT NODE 600
-
- WALL FRAMING 600 790 20 92